U.S. NAVY
EXHIBIT 1—AVERAGE AGE OF SHIPS IN THE U.S. NAVY FLEET
OVER THE NEXT TEN YEARS
1989 1990 1991 1992 1993 1994 1995 1996 1997 1998
Battleships 46 47 48 49 50 51 52 53 54 55
Cruisers 21 16 16 15 15 16 17 18 19 20
Destroyers 19 19 18 16 17 17 18 19 20 21
Frigates 12 13 14 15 16 17 18 19 20 21
Carriers 27 26 27 28 28 27 28 28 29 30
Submarines 16 16 17 17 18 18 19 20 21 22
Tenders 27 28 29 30 31 32 33 34 35 36
Logistics Ships 25 24 25 25 25 26 27 27 28 29
Amphibious Ships 19 18 19 20 20 21 22 23 24 25
Mine Warfare Ships 33 28 23 22 23 24 25 26 27 28
Patrol Combatants 8 9 10 11 12 13 12 13 9 10
Survey Ships 18 18 17 17 18 19 20 21 22 23
Sealift Ships 15 16 17 18 19 20 21 22 23 24
Misc 20 21 22 23 24 25 26 27 28 29
Note: Ships already contracted or currently in service are included in the averages. Excluded are ships known to be earmarked for
decommissioning over the next several years. The forecast assumes no further orders are placed and Navy maintains its current
level of fleet inventory. In effect, the data represent the aging process which will occur if the Navy orders no further ships.
Source: International Maritime Associates, Inc.. U.S. Navy Shipbuilding in a Period of Uncertainty, February 1989.
EXHIBIT 2—ASSESSMENT OF FUTURE U.S.
CURRENT SITUATION
ten year build-up completed—480 to 580 ships
big impact on industry—addictive, many companies now Navy
dependent
problems have accumulated—technical shortfalls, cost over-
runs, procurement scandal
stalemate exists—major decisions on program direction await-
ing next administration
FUTURE PROGRAM DRIVERS
goals for fleet size and composition depend on Navy's percep-
tion of its defense role
aging ships, technology advances create basic replacement
needs
DOD's priorities for allocating financial resources sets Navy's
funding limit
future international developments impact Navy require-
ments—foreign base closures, conventional arms reduction
agreements
current problems could erode political support for key Navy
programs—particualry DDG 51, SSN 21
shift in congressional positions may impact support for Navy
programs in Congress
SUBMARINES
SSN 688 funding may end earlier than planned—now overlaps
with SSN 21 start-up
SSN 21 continues to be controversial—expensive, slow
Trident building goal depends on missile treaty negotiations
new roles proposed for submarines—anti-air, battle surveil-
lance
DARPA/Navy submarine R&D could produce major changes in
sub design
AN/BSY 2 combat system problems could be big issue
SURFACE COMBATANTS
DDG 51 program could be expanded beyond 29 ships
Aegis system shortfalls,ship cost overruns casting shadow over
DDG 51 program
major effort initiated to develop revolutionary designs for sur-
face ships
frigate modernization program being considered
electric drive designated as propulsion system for future ships
CARRIERS
12, 13 or 15 carrier groups—big issue affecting future surface
force requirements
new carrier orders and CV modernizations in 1990's depend on
carrier force objectives
TENDERS
very old inventory
possible AR program to enhance forward repair capability
NAVY SHIP CONSTRUCTION REQUIREMENTS
AMPHIBIOUS SHIPS
next several years include LSD 49 and LHD orders
LPH and/or LPD replacement program to begin mid-1990's
LCAC orders to reach 90 units
COMBAT LOGISTICS SHIPS
fleet capability gap said to exist—despite AOE, TAO procure-
ments
AE building program—technical issues still to be resolved
PATROL COMBATANTS
PXM program planned for early 1990's
MINE WARFARE
MHC, MCM programs continue to have technical problems
new designs under review—including air cushion vehicle for
minehunting
OCEAN SURVEY AND SURVEILLANCE
more TAGOS surveillance ships to be ordered
SWATH "A" bigger than TAGOS 19
oceanographic ships—some SWATH designs
SEALIFT SHIPS
Army wants more sealift capability
Navy studying procurement of new fast sealift ship
additional crane ships—must be funded by DOT
replenishment tankers—build/charter program to replace
Sealift tankers
SERVICE CRAFT
Inventory approaching block obsolescence
creative procurement methods likely
MPLICATIONS FOR INDUSTRY
technolgoy push developments getting greater attention in
Navy
fewer ships, increasingly expensive, complex—business will
support fewer players
technology changes will open new opportunities—fibre optics,
composite armor, stealth concepts, ship survivability, etc.
ships will be designed for minimizing M&R toll
DEVELOPMENTS TO WATCH
fewer dollars, rapidly growing unit costs will produce internal
clash for available funds
overruns/claims to cause procurement shake-up, contracting
rules to change
sustained attack of Aegis technology threatens pace of DDG 51
program
Navy under pressure to study and introduce new concepts—
not simply buy more of the same
Source: International Maritime Associates, Inc., U.S. Navy Shipbuilding in a Period of Uncertainty, February 1989
32
(continued)
ty. Trident construction will likely
end at 20 units. Sixteen are now in
service or under contract. Future
construction will probably continue
at the rate of one per year through
1992.
Attack submarines—Con-
struction of six to eight additional
SSN-688s and 20 to 25 SSN-21s has
been planned over the next 10 years.
However, budget pressures are like-
ly to cause cancellation of some of
the remaining SSN-688s.
The SSN-21 program could prove
very controversial due to program
cost. The Navy projects SSN-21 fol-
low ships will be about 20 percent
more costly than the SSN-688. This
seems very optimistic—considering
the SSN-21 is far more complicated
and one third larger than the SSN-
688. The SSN-21 cost estimate is
going to be a major target for criti-
cism over the next few years.
The Navy is now studying new
roles for attack submarines—in-
cluding antiair capability—which
may lead to major changes in sub-
marine design. The Defense Ad-
vanced Research Projects Agency
(DARPA) has been assigned respon-
sibility for assessing promising con-
cepts which could lead to major
breakthroughs in submarine tech-
nology. Funding of $95 million has
been provided this year for the
DARPA program. The Navy and
DARPA work in this area could pro-
vide many new business opportuni-
ties.
CARRIERS
The goal of 15 operational car-
riers is very controversial. Aircraft
carriers are enormously expensive to
build, deploy and maintain. The
four CVNs now under contract are
to offset retirements of three older
CVs. But five instead of three
CVs—and possibly the USS Enter-
prise (CVN-65)—may be retired in
the 1990s for budget-cutting rea-
sons.
It's possible that the next admin-
istration could stretch spending on
CVN-75—maybe even CVN-74.
However, the contract for both
ships has been awarded and a major
cancellation cost would be incurred
should there be a change of plans.
Cancellation would be unlikely.
CRUISERS/DESTROYERS
The Navy's goal to build 29 DDG-
51s may be pushed higher. There is
again talk of a 60-ship force require-
ment—which would provide a five
to six per year construction program
through the 1990s. The higher fig-
ure is in line with the number of
DDGs originally planned in the ear-
ly 1980s.
However, future requirements for
DDGs largely depend on the num-
ber of carriers and battleships in
service. Each carrier group and sur-
face action group roughly requires
three missile destroyers for protec-
tion. Any cut in major ships in ser-
vice (carriers or battleships) will re-
duce DDG force requirements.
Budget constraints will also play
a major role in limiting expansion of
the DDG building program. These
ships must compete with attack
Digital Wave Publishing